Alsónémedi -Implementation of vacuum sewage system (3 km)

Cegléd - Reconstruction of low-pressure gas pipe

Eger - Reconstruction of low-pressure gas pipe

Királyvölgyi Apartment Complex, Tinnye and Pilisjászfalu, Hungary (2001) - Construction of water network (6.5 km)

Emőd Engineering Works, Motorway M3 (2002) - Construction of sewage and rainwater pipe networks (2,900m) Water pipe network, Gas pipe network, Depressed sewer network

”Kiskastély Apartment Complex”, Balmazújváros, Hungary (2002) - Construction of whole public services Building of water and gas pipes, and sewer network

TVK Co., Tiszaújváros, Hungary (2002) - Construction of Water Treatment Plant, drinking and industrial water pipes Building of rainwater pipes and sewers

Building of Control Center: Construction of drinking water and sewage system

Olefin 2 Project: ø 600mm and ø 800mm, Construction of Rainwater network

Újszentmargita-Bödönhát, Hungary (2003) - Construction of Drinking water network (3km)

Veres Péter Housing Estate, Nyírtelek-Ferenctanya, Hungary - Construction of gas distribution pipes

Nagykálló-Ludastó, Hungary - Construction of gas distribution pipes

Nyírtelek-Dankóbokor - Construction of gas distribution pipes

Regional Dump public services pipes, Hajdúböszörmény, Hungary (2004) - Drinking water, sewage, rainwater pipelines

Mini Apartment Complex, Hajdúböszörmény, Hungary - Construction of public services pipes (drinking water, sewage, gas pipes)

Mátramindszent, Hungary (2005) - Construction of gravitational and depressed sewage treatment works

Balmazújváros, Hungary (2005) - Construction of gravity sewage treatment plant with cleaner works

Regional Dump, Tiszafüred, Hungary (2005) - Construction of public services pipes (drinking water, sewage, rainwater, and leechate pipes) Building and engineering of sewer liftaway.

TESCO Hypermarket, Mezőkövesd, Hungary (2006) - Construction of Rainwater pipe network with cleaner works

HM Petrol Base, Hetényegyháza (2006) - Installation of Sepurator mud-trap and oil separator equipment in rainwater runoff network

Hortobágy-Halastó, Hungary (2006)

Construction of PE Outer-Area Drinking water pipeline (6,000m)

Mechanical and electric Installation of Pressure enhancer

Construction of inner-area distribution network with 40 household connections

Liget Apartment Complex, Phase II, Debrecen, Hungary (2006)

Construction of the entire middle-pressure gas distribution network